Every summer, the same conversation happens on job sites: the thermometer says 95°F, the crew is in coveralls, and someone asks, “Is it too hot to work?” The honest answer is that air temperature alone cannot tell you. The metric built for exactly this question is WBGT — wet bulb globe temperature — and it is also the metric your written heat illness prevention plan should be built on. This guide explains what WBGT actually measures, how the thresholds work once PPE enters the picture, and how to turn the numbers into a written plan that holds up to an OSHA inspection.
What WBGT is (and why the heat index is not enough)
The heat index combines air temperature and humidity, assumes shade and light wind, and assumes a person in light clothing. Your crew works in full sun, around hot surfaces, often in protective clothing. WBGT was designed for those conditions. It combines three measurements:
- Natural wet bulb temperature — evaporation and humidity (how hard it is for sweat to cool the body)
- Black globe temperature — radiant heat from the sun and hot surfaces
- Dry bulb temperature — plain air temperature
Outdoors with sun load, the formula is:
WBGT = 0.7 × wet bulb + 0.2 × globe + 0.1 × air temperature
Indoors or without sun load it is 0.7 × wet bulb + 0.3 × globe. Note the weighting: humidity-driven cooling capacity counts for 70% of the index. That is why two days at the same air temperature can carry completely different risk — and why a plan based on the weather app will eventually fail someone.
The thresholds: work/rest cycles and hydration
WBGT becomes operational when you pair it with the ACGIH screening criteria (closely mirrored by NIOSH). For acclimatized workers, the screening values are roughly:
| Work / rest allocation | Light work | Moderate work | Heavy work |
|---|---|---|---|
| 75–100% work | 30.0°C (86°F) | 26.7°C (80°F) | 25.0°C (77°F) |
| 50–75% work | 30.6°C (87°F) | 28.0°C (82°F) | 25.9°C (78°F) |
| 25–50% work | 31.4°C (88°F) | 29.4°C (85°F) | 27.9°C (82°F) |
| 0–25% work | 32.2°C (90°F) | 31.1°C (88°F) | 30.0°C (86°F) |
Unacclimatized workers get lower limits — typically 2–3°C below these values. Above the applicable limit, the answer is not “push through”: you increase rest allocation, reschedule the heavy work, or stop. Hydration runs alongside: up to 1 quart (about 1 liter) of water per hour, with electrolytes when sweating continues beyond two hours. Always verify against the current ACGIH TLV booklet for your exact situation — treat the table above as a planning summary, not a substitute.
The step most plans miss: the PPE adjustment
Here is where generic heat plans break. The thresholds above assume standard work clothing. Protective clothing traps heat and blocks evaporation, so ACGIH applies a clothing adjustment value that you add to the measured WBGT before comparing it with the table:
| Clothing / PPE ensemble | Add to measured WBGT |
|---|---|
| Standard work clothes or woven coveralls | 0°C |
| Double-layer woven clothing | +3°C |
| Impermeable coveralls | +6°C |
| Fully encapsulating suit | +11°C |
Worked example: your meter reads WBGT 27°C. The crew wears impermeable chemical coveralls, so the effective exposure is 27 + 6 = 33°C — above even the most permissive cell in the table. The correct call is to stop or fundamentally change the job (different hours, mechanical assists, cooling), not to shorten the rest break debate. If your plan does not contain this adjustment step, it will clear crews for work that the numbers actually prohibit.
What a written heat illness prevention plan must contain
Several state-plan states (California, Washington, Oregon, Minnesota) already require a written plan by rule, OSHA enforces heat under the General Duty Clause and its National Emphasis Program, and the proposed federal heat standard would make a written plan mandatory nationwide. A plan that satisfies inspectors — and actually protects people — covers eight elements:
- Responsibility — a named person per site/shift who monitors conditions and can stop work.
- Monitoring method — WBGT measured on site (not a phone app), how often, and where readings are logged.
- Thresholds and actions — your work/rest table, including the PPE clothing adjustment, and what happens at each level.
- Water, rest, shade — quantities, locations, and the rule that rest is taken before symptoms, not after.
- Acclimatization schedule — new workers start near 20% of normal heat exposure and add about 20% per day; returning workers follow a 50/60/80/100% ramp over four days, with close observation for the first two weeks.
- Emergency response — recognizing heat stroke (confusion, hot dry skin, collapse), aggressive cooling first, transport second, and who calls it in.
- Training — workers and supervisors, in a language they understand, documented with dates and attendance.
- Review trigger — the plan is revisited after any heat incident, near-miss, or change in PPE or process.
Common mistakes we see in real plans
- Using the heat index or air temperature as the trigger. Both ignore radiant heat and PPE — the two factors that injure people in industrial settings.
- One threshold for everyone. No acclimatization distinction, no PPE adjustment, no difference between light inspection work and heavy manual labor.
- A plan that lives in a binder. If the foreman cannot see today’s WBGT, today’s work/rest cycle, and today’s responsible person on one page, the plan is decorative.
- No records. Unlogged readings and undocumented training are treated by inspectors as things that never happened.
FAQ
Is a written heat illness prevention plan legally required?
It depends on your state. California, Washington, Oregon, and Minnesota require one under their state rules. Federally, OSHA currently enforces through the General Duty Clause and its heat emphasis program, and the proposed federal heat injury and illness prevention standard would require a written plan for covered employers. Even where it is not yet mandated, the written plan is the first document requested after a heat incident.
Can I use a weather app instead of a WBGT meter?
Apps estimate conditions at a weather station, in shade assumptions, and know nothing about your radiant heat sources or PPE. Use app data for morning planning if you like, but compliance decisions and work/rest calls should come from WBGT measured or calculated for the actual work area.
How often should WBGT be re-checked?
At minimum at the start of the shift and whenever conditions change materially — as a rule of thumb, hourly during the hot part of the day, and always before a crew starts a heavy task in PPE.
Where do the work/rest numbers come from?
The screening criteria are published by ACGIH (TLV) and mirrored in the NIOSH criteria document. They are the reference OSHA points employers to. Recheck them annually; the values are updated as the TLV booklet is revised.
Turn this into your plan in about ten minutes
We built a free tool that does the arithmetic in this article for you: enter temperature, humidity, sun exposure, workload, and the PPE your crew wears, and it returns the WBGT, the clothing-adjusted exposure, the work/rest schedule, and a draft written heat illness prevention plan you can adapt and keep on file.
Open the free WBGT Heat & PPE Work/Rest Calculator →
We are a PPE team, not a software company — the tools are free, with no sign-up. If the calculator or the plan draft is missing something your site needs, tell us in the comments or by email; practitioner feedback is literally how these tools get their next feature.